Rollout order
The function withholds composed resources from the desired state until what
AICR orders before them is observed Ready. This is the gate. It orders
creation only.
Every Release sets spec.forProvider.wait: true. provider-helm then
reports a Release Ready only once the Helm release’s resources are up,
and that’s the signal the gate reads.
The signal is about the installation. provider-helm waits for the resources
while it installs or upgrades a release. Afterward it reports the Release
Ready for as long as the Helm release is deployed and matches the
Release’s specification, even when its pods have stopped.
An upgrade interrupts the signal for longer than it runs. provider-helm
marks a Release unready when it starts to upgrade it, and looks at it
again at its next poll, which comes every 10 minutes by default. A component
whose values or version changed reports unready until then, and the
composite resource with it, although Helm finished the upgrade long before.
Nothing is withheld in the meantime, because the gate leaves what’s already
deployed alone. provider-helm’s --poll flag shortens the wait.
The rules
For each component:
- its pre-manifest
Objects wait for the components it depends on; - its
Releasewaits for those dependencies and for its pre-manifestObjects; - its post-manifest
Objects wait for itsRelease.
A manifest-only component has no Release. Its Objects all wait for its
dependencies, and as somebody else’s dependency it’s ready when every
Object it emitted is.
A dependency counts only when the function deploys it. One that’s skipped,
turned off by the recipe or left out by componentClasses is satisfied.
Every resource the gate withholds raises a Normal result that says what it
waits for. The status summary lists a component
under pendingComponents while its Release, or an Object of a
manifest-only component, is withheld.
Crossplane’s circuit breaker
Crossplane limits how often watch events reconcile one composite resource. It allows a burst of 100 events and one more per second after that, counting each change to the composite resource and to the resources it composes. The resources of a rollout are created together and each reports its status more than once, which can use up the burst within seconds. In the end-to-end suite a recipe of three components did so three seconds after its composite resource was created.
Crossplane then sets the condition Responsive to False with the reason
WatchCircuitOpen. For the next five minutes it lets one event through
every 30 seconds. The rollout continues, but each step waits for the next of
those reconciles, and the status summary lags by as much.
If that’s too slow, raise --circuit-breaker-burst in Crossplane’s
arguments. The suite’s recipe was ready after 64 seconds with the default
and after 5 seconds with a burst of 1000.
Live resources
A resource that has already been observed is never withheld. The gate must not tear down a live resource because a sibling went unready for a moment.
Turning it off
skipDeploymentOrder: true emits every component at once. Use it only when
something else orders the installs, or when the order doesn’t matter.